Fondazione Fiera Milano upgraded its roofs by removing old coverings and installing new aluminum alloy panels designed for a 20° tilt photovoltaic system, with a capacity of approximately 8.2 MW. The intervention, conducted over multiple years to accommodate event scheduling, covered more than 200,000 sqm of roof area with slopes under 1.5%.
EOS provided Technical Advisory services from the design stage, including contract review, project analysis, and scheduling. In collaboration with the Politecnico di Milano, EOS assessed the feasibility of this highly complex structure.
In the construction phase, EOS has carried out the Works Management of a "Sample" cover of about 8,000 square meters analyzing the progress of the work, Checking that the work carried out is in conformity with the design and examining the metallic materials used by means of laboratory tests.
EOS also carried out the static and building tests of the roofs, analysing the final design, defining the test tests with which to test the entire system, ensuring the quality of the results obtained, verifying the results of laboratory tests on the materials used and ensuring that the work carried out is in conformity with the project.